Organizational
                  Requirements – monitor trends 
                  As we said earlier, it’s
                  not enough to look at snapshots in time when trying to control
                  a project. A trend chart gives
                  additional information. In this example, the team is getting
                  behind schedule. What is a primary reason for this? Not enough
                  resources? Sure enough, cost expenses are under plan. But notice
                  what happens near the end of September: the team is getting
                  further behind schedule and cost is overrun. This situation
                  needs immediate attention. 
                 
  |