Cost/Schedule
                  Control – weekly and cumulative SPI (alternate) 
                  Remember
                  the guidelines on when to consider changing the baseline (PV):
                  25% to 40%
                  into the project? The statistical information for those guidelines
                  comes from SPI data on medium to high
                  risk projects. The chart
                  on this page shows weekly and cumulative SPI (alternate) for
                  a low risk project. Notice how the cumulative SPI (alternate)
                  stabilizes after about 15% complete? This example stabilized
                  more quickly than medium to high risk projects. 
                 
  |