Are
                    there any fixed principles 
                    for subdividing the WBS? (continued) 
        This example shows the relationship between a product breakdown structure
        and a work breakdown structure. Notice how the WBS includes all the work
        that goes into the project, not just the work that goes into the product.
        In other words, work elements like project management, systems engineering,
        and integrated logistics are also work activities. If you forget to include
        these in the WBS you are leaving out vital parts of the scope. These
        are the coordination and communication tasks that “glue” the
        product components into a complete project. 
                 |